US-31/M-72 (Grandview Parkway) in Traverse City substantially complete, fully open
October 28, 2024
TRAVERSE CITY, Mich. - The Michigan Department of Transportation’s (MDOT) $24.7 million US-31/M-72 (Front Street and Grandview Parkway) project in Traverse City is now substantially completed and all lanes were fully opened ahead of schedule.
"We’re here today to celebrate its completion not just because of MDOT, our contractor, and our consultant, but because of the commitment that this community has made to making this project a success," said State Transportation Director Bradley C. Wieferich at a ribbon cutting event today at Traverse City’s MINI Park near the newly rebuilt intersection of Grandview Parkway and Front Street. “Thanks to all the businesses, the residents, the drivers, pedestrians and bicyclists for all their patience during the work. We know it’s not easy.”
Wieferich was joined in providing remarks by Traverse City Mayor Amy Shamroe, Traverse City Downtown Development Authority Executive Director Harry Burkholder, Team Elmer’s Project Manager Sean Sebela, TART Trails Trail Planning and Management Director Chris Kushman, Norte Executive Director Jill Sill, and State Rep. Betsy Coffia, as well as other local officials and community leaders. A video news release is posted on MDOT’s YouTube channel.
Traverse City Manager Liz Vogel commented on the completion of the MDOT project, highlighting the collaborative effort and substantial upgrades. “The city is thrilled to see this significant investment in our community come to fruition, enhancing infrastructure for residents and visitors alike. We commend Team Elmer’s, a valued local company, for their dedication to completing the project ahead of schedule. Additionally, we’re pleased that the timing allowed us to invest $3.2 million into utility infrastructure improvements, maximizing efficiency and long-term benefits for our city.”
Some minor work remains, including sign installation and signal work that will require intermittent lane closures over the next few weeks. The project was originally scheduled to be completed by mid-November.
A separate but concurrent project by the City of Traverse City to expand and improve the TART Trail along the parkway is also complete, except for placement of signs. Team Elmer’s is the prime contractor for both projects.
In addition to rebuilding the roadway, this project included replacing concrete curb and gutter, upgrading sidewalk and ramps, improving storm sewer, and repairing the Murchie Bridge over the Boardman River. The City of Traverse City also invested $3.2 million to replace underground water and wastewater utilities as part of the contract.
Based on economic modeling, this investment directly and indirectly supports 351 jobs.
State and local officials celebrated early completion of the US-31 rebuilding project with a ribbon cutting today at the newly rebuilt Grandview Parkway/Front Street intersection. Left to right: TART Trails Trail Planning and Management Director Chris Kushman, Team Elmer’s Project Manager Sean Sebela, Traverse City Downtown Development Authority Executive Director Harry Burkholder, Norte Executive Director Jill Sill, State Rep. Betsy Coffia, Traverse City Mayor Amy Shamroe, State Sen. John Damoose’s Deputy Chief of Staff Dakota Baker, State Transportation Director Bradley C. Wieferich, and Team Elmer’s Communications and Marketing Director Tonya Wildfong.
A view of US-31 (Grandview Parkway) fully reopened following early completion of MDOT’s $24.7 million rebuilding project in Traverse City.
A view of US-31 (Front Street) in Traverse City at the newly rebuilt intersection with Grandview Parkway.