M-20 resurfacing begins March 17 in Midland County
March 03, 2025
MT. PLEASANT, Mich. -The Michigan Department of Transportation (MDOT) is investing $21.9 million to resurface and improve M-20 from M-30 (Meridian Road) to Currie Parkway west of Midland. Work will include 5.7 miles of resurfacing, concrete curb and gutter work, shoulder widening, joint repairs, storm sewer work, guardrail upgrades and pavement markings.
Counties:
Midland
Highway:
M-20
Closest community:
Midland
Start date:
Monday, March 17, 2025
Estimated end date:
November 2025
Traffic restrictions:
Traffic will be maintained using lane closures and traffic shifts. One lane will be open in each direction.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 209 jobs.
Safety benefit:
This work will provide drivers with fresh pavement markings and a smoother, safer driving surface. Closing lanes during this type of work is necessary to provide the safest work area possible for crews and motorists.